Develop a network drawing for hill construction

Develop a network drawing for hill construction

Problem –

Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2009, SWU hired the legendary Phil Flamm as its head coach.

TIME ESTIMATES (DAYS)

DESCRIPTION

PREDECESSOR(S)

OPTIMISTIC

MOST LIKELY

PESSIMISTIC

CRASH COST/DAY

Bonding, insurance, tax structuring

20

30

40

$1,500

Foundation, concrete footings for boxes

A

20

65

80

3,500

Upgrading skybox stadium seating

A

50

60

100

4,000

Upgrading walkways, stairwells, elevators

C

30

50

100

1,900

Interior wiring, lathes

B

25

30

35

9,500

Inspection approvals

E

0.1

0.1

0.1

0

Plumbing

D, F

25

30

35

2,500

Painting

G

10

20

30

2,000

Hardware/AC/metal workings

H

20

25

60

2,000

Tile/carpet/windows

H

8

10

12

6,000

Inspection

J

0.1

0.1

0.1

0

Final detail work/cleanup

I, K

20

25

60

4,500

One of Flamm’s demands on joining SWU had been a new stadium. With attendance increasing, SWU administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to expand the capacity at its on-campus stadium. Adding thousands of seats, including dozens of luxury skyboxes, would not please everyone. The influential Flamm had argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it. The job now was to get construction going immediately after the 2015 season ended. This would allow exactly 270 days until the 2016 season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked President Wisner in the eye. “I guarantee the team will be able to take the field on schedule next year,” he said with a sense of confidence. “I sure hope so,” replied Wisner. “The contract penalty of $10,000 per day for running late is nothing compared to what Coach Flamm will do to you if our opening game with Penn State is delayed or canceled.” Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be mud if the 270-day target was missed. Back in his office, Hill again reviewed the data (see Table 3.6 ) and noted that optimistic time estimates can be used as crash times. He then gathered his foremen. “Folks, if we’re not 75% sure we’ll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days-also for 240 days. I want to be early, not just on time!”

Discussion Questions

1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take?

2. What is the probability of finishing in 270 days?

3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.