LP3 Assignment: Earned Value Management

Part II: COMPLETE: Project Control/Earned Value Management
Note: Watch this YouTube video, hosted by Defense Acquisition, for tips to complete this section: Basic EVM Part 1.

As the project manager on your neighbor’s shed, you have the following information on Day 20:

BAC $10,000/20
Work: See WBS for work to 20 days (See WBS)
Schedule: 30 days 20 days
(BCWS) Budgeted Cost of Work Scheduled: Day 20: (See estimate)
(BCWP) Earned Value Actual Cost of Work Performed: $6,500
(ACWP) Actual Cost of Work Performed: $6,200

Complete the following analysis and answer the questions below:
Percent Scheduled: (BCWS/BAC)*100 _______
Percent Spent: (ACWP/BAC) * 100      _______
Percent Complete: (BCWP/BAC) * 100 _______

Analyze the situation:
• Are you on Track?
• Are you on budget?
• Are you on schedule?
• What deviations/ variances exist?
• What risks are we monitoring?
• What issues do we need to resolve?
• What lessons have we learned?