MGSC 303 Assignment 4 SP 2017

MGSC 303 Assignment 4 SP 2017
1. Complete the MRP schedule for the product below.

Product ALot Size = 100 Safety Stock = 50

Lead Time = 1 week Allocated = 200 In hand =600

WEEKS
1
2
3
4
5

Gross requirement
200
500
300
800
400

Scheduled receipt
100

Available

Net requirements

Planned order receipts

Planned order releases
2. Product X has the structure given below.
X
P3 R2 S4
Q3 T2 V3
a) If 60 units 0f product X has to be produced, compute the bill of materials.

ITEM QUANTITY
P
R
S
Q
T
V
b) Given the following lead times draw the time phased product structure for X.
If delivery is desired in week 10 from now.

ITEM LEAD TIME
IN WEEKS
X 1
P 1
Q 2
R 3
S 2
T 3
V 2
1 2 3 4 5 6 7 8 9 10

MGSC 303 Assignment 4 SP 2017
1. Complete the MRP schedule for the product below.

Product ALot Size = 100 Safety Stock = 50

Lead Time = 1 week Allocated = 200 In hand =600

WEEKS
1
2
3
4
5

Gross requirement
200
500
300
800
400

Scheduled receipt
100

Available

Net requirements

Planned order receipts

Planned order releases
2. Product X has the structure given below.
X
P3 R2 S4
Q3 T2 V3
a) If 60 units 0f product X has to be produced, compute the bill of materials.

ITEM QUANTITY
P
R
S
Q
T
V
b) Given the following lead times draw the time phased product structure for X.
If delivery is desired in week 10 from now.

ITEM LEAD TIME
IN WEEKS
X 1
P 1
Q 2
R 3
S 2
T 3
V 2
1 2 3 4 5 6 7 8 9 10