ODS 333Operations and Logistics Management Midterm 1
1.(20/100 Points) George makes bearing balls in his Miami plant. With recent increases in his costs, he has a newfound interest in efficiency. George is interested in determining the productivity of his organization. He would like to know if his organization is maintaining the manufacturing average of 5% increase in productivity per year.
He has the following data representing last year and this year. Assume both years the units produced are 10,000.
Last Year | This Year | |
Labor (hours) | 300 | 275 |
Resin (pounds) | 50 | 45 |
Capital invested ($) | 10,000 | 11,000 |
Energy (BTU) | 3,000 | 2,850 |
George determines his costs to be as follows:
What is George’s Multifactor Productivity for Last year?What is George’s MultifactorProductivity for this year?What was George’s % increase in Multifactor Productivity from last year to this year?
ODS 333Operations and Logistics Management Midterm 1
Risk Factor | Weights | Poland | Mexico | South Korea |
Political stability | .35 | 6 | 5 | 6 |
Financial strength | .15 | 10 | 6 | 9 |
Sustainability policies | .20 | 8 | 7 | 8 |
Cost | .25 | 7 | 9 | 10 |
Quality | .05 | 4 | 8 | 7 |
Which country is the best option that they should choose?
ODS 333Operations and Logistics Management Midterm 1
(a) (10 Points) Based on life cycle cost, which bus is the best option?
(b) (5Points) How many miles does the school district need to put on a bus for break-even?
(c) (5 Points) What is the payback period?
ODS 333Operations and Logistics Management Midterm 1
(a) (3 Points) Draw a project network.
(b)(7 Points)Develop the activity schedule for the project (schedule each activity).
(c) (4 Points) Identify the critical path.
(d) (4 Points) Does it appear reasonable that construction of the athletic complex could begin oneyear (52 weeks) after the decision to begin the project with the site survey and initial design plans?What is the expected completion time for the project?
(e) (1 Point) Can activity D be delayed without delaying the entire project? If so, by how manyweeks?
(f) (1 Point) Can activity C be delayed without delaying the entire project? If so, by how manyweeks?
ODS 333Operations and Logistics Management Midterm 1