Use the following WBS and duration information for a project to build a new website. Prepare a Gantt chart and a precedence diagram. Determine the critical path.
1.
Initiating
1 week
2.
Planning
4 weeks, starting after Initiating ends
3.
Executing
3.1 Conduct User Interview
6 weeks, starts after Initiating ends
3.2 Conduct User Survey
4 weeks, starts midway through User Interviews
3.3 Site Content
3.3.1 Develop Templates
12 weeks, starts after User Interviews and User Survey end
3.3.2 Write Articles
8 weeks, stats anytime after Site Content begins
3.3.3 Prepare FAQ
2 weeks, starts after User Interviews and User Survey ends
3.4 Design Site
8 weeks, starts after User Interviews and User Survey end
3.5 Build Site
16 weeks, starts after Design Site ends
3.6 Perform Integration Testing
2 weeks, starts after Build Site ends
3.7 Conduct Acceptance Tests
2 weeks, starts after Integration Testing ends
4.
Controlling
runs for entire duration of project
5.
Closing
1 weeks, follows Acceptance Testing