At what project duration do we achieve the lowest total

At what project duration do we achieve the lowest total/Managerial Economics

You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project direct costs are given below.

2289_68-B-E-M-E (2128)-1.png

The network for this project is given below.

859_68-B-E-M-E (2128)-2.png

The indirect costs for the project are determined on a daily duration basis and are given below:

Total indirect costs for 16 days of project duration: $ 600
Total indirect costs for 15 days of project duration: $ 400
Total indirect costs for 14 days of project duration: $ 200
Total indirect costs for 13 days of project duration: $ 100

At what project duration do we achieve the lowest total project cost(i.e., direct plus indirect costs)?
(a) 16 days
(b) 15 days
(c) 14 days
(d) 13 days

Order from us and get better grades. We are the service you have been looking for.